Wow when I type week 4 that seems like a long time. But remember it is the beginning of the fourth week so really only 3 weeks into the project. Today 2 drywall guys got here around 10:30 and they left just after noon. And they never came back! They worked on the ceiling joints and taped most of the side wall seams. So... I guess they will be back tomorrow.🤞🏻
A setback today though. The slate we picked for the foyer has been delayed until the middle of May. It was suppose to blilld next week. Contractor says he will work around it and finish that area last. Supposedly it is on a boat coming from Africa. I hope it was not one of the ones waiting to get through the Suez Canal where a ship was stuck for over a week.
1 comment:
What a difference dry wall can make! It’s going to be great! I admire you for how well you are handling all of this!
❤️Jools
Post a Comment